The procedure from choosing a beneficiary to the board of review, with the four approvals that all fall before any work begins and the things around the spine that are not steps at all.

26 steps (23 parts inside them). 6 steps and parts depend on questions you have not answered yet. · Version 1, published 9 August 2026 · About The Eagle Scout Service Project

This is the whole plan: everything that could apply to anybody. Answering the 3 questions at the address above takes out the parts that are not for you.

Which of this applies to you

You have not answered anything yet, so this is the whole plan: everything that could apply to anybody. Answering 3 short questions will take out the parts that are not for you.

Your progress

30 steps can be started now; 18 are waiting on something else.

Clear ticks

Your ticks are kept in this browser, so they will still be here next time. They are in the address as well, so a link to this page carries them to another device.

The steps

Stage 1 of 16

6 steps

Stage 2 of 16

2 steps
  • 9.0.2.2. Work begins after the Life Scout board of review Often forgotten Requirement

    Work on a project, planning included, begins after the Life board of review. That is not meant to stop an enthusiastic Star Scout from talking to a Scoutmaster, a religious leader or a principal about what a good project might be.

    Usually comes after 9.0.2.0. Eagle Scout requirement 5.

  • 9.0.2.15. What insurance covers, and what it does not Requirement

    The general liability policy covers official Scouting activities, with registered adult leaders primary and unregistered adults covered in excess of their own insurance. Accident and sickness cover is a council option, mostly secondary and limited to registered youth and adults. Chartered organization cover must not be assumed.

Stage 3 of 16

1 step

Stage 4 of 16

1 step
  • 9.0.2.6. It must benefit somebody other than Scouting America Often forgotten Requirement

    Projects must not be performed for Scouting America or its councils, districts, units or camps. The unit's own chartered organization is certainly a good candidate, as are other international Scouting organizations and other youth organizations.

    Usually comes after 9.0.2.5. Choose a beneficiary and a project.

    The exception people miss is the unit's own chartered organization, which the Guide calls certainly a good candidate. A project for the church that charters the troop is fine; a project for the troop is not.

Stage 5 of 16

1 step

Stage 6 of 16

1 step
  • 9.0.2.7. The five tests of an acceptable proposal Approval

    Sufficient opportunity to meet the requirement; feasible; safety issues will be addressed; action steps for further detailed planning are included; and the Scout is on the right track with a reasonable chance of a positive experience. When the reviewer is satisfied these can be met, approval is granted.

    Usually comes after 9.0.2.7. Write the proposal.

    These five are the whole test. A reviewer who is satisfied they can be met grants approval, and a reviewer who wants more than the workbook describes is asking for something the Guide does not permit them to ask for.

Stage 7 of 16

4 steps, 1 ticked
  • 9.0.2.7. The beneficiary approves Approval

    The organisation benefiting from the effort. The workbook carries a beneficiary information sheet, "Navigating the Eagle Scout Service Project", written to explain the requirement and the rights that come with the benefit.

    Usually comes after 9.0.2.7. The five tests of an acceptable proposal.

  • 9.0.2.7. The unit leader approves Approval

    One of the four signatures named in requirement 5 itself.

    Usually comes after 9.0.2.7. The five tests of an acceptable proposal.

  • 9.0.2.7. The unit committee approves Often forgotten Approval

    The unit committee is responsible for this approval. A troop, crew or ship committee may designate representatives to act on its behalf, and that is a unit decision: neither district nor council may say how many committee members must be involved.

  • 9.0.2.7. The council or district approves Approval

    The reviewer works through the proposal with the Scout, and space is provided in the workbook to record the suggestions, cautions and concerns that a thorough review generates. Every attempt should be made to finish the approval in one meeting.

    Usually comes after 9.0.2.7. The five tests of an acceptable proposal.

Stage 8 of 16

1 step
  • 9.0.2.7. Nothing starts before all four approvals are in Milestone

    The proposal must be approved before you start. That covers the project itself and any fundraising for it.

    Usually comes after 9.0.2.7. The beneficiary approves, 9.0.2.7. The unit leader approves and 9.0.2.7. The council or district approves.

    This is the single most common way an Eagle project goes wrong: a Scout starts collecting materials, or runs a car wash, before all four approvals are in. It is worth saying at the point the project is first discussed rather than after.

Stage 9 of 16

2 steps
  • 9.0.2.7. Started early: normally a different project May not apply Often forgotten Decision

    Scouts sometimes begin fundraising, or the work itself, before approval. Normally the Scout should then select a different project. Where circumstances are compelling, so that leniency can be extended and a lesson learned without significant detriment to the project's purpose, the Scout may carry on and have it approved after the fact.

    You have not answered "Did any work or fundraising begin before the proposal was approved?" yet.

    Usually comes after 9.0.2.7. Nothing starts before all four approvals are in.

  • 9.0.2.9. Work with the project coach Recommended Task

    The subject matter expert on the process and standards, designated by the council or district. Meets the Scout after the proposal is approved and before the plan is written, asks how the Scout will plan it, flags what could stop work or create a safety issue, reviews the plan for strengths, weaknesses and risks, and helps prepare for the board of review.

    Usually comes after 9.0.2.7. Nothing starts before all four approvals are in.

    3 parts

Stage 10 of 16

1 step
  • 9.0.2.3. Write the detailed project plan Task

    Planning and development require forethought, effort and time, sometimes more than execution does, and they are detailed once the proposal is approved. That order is deliberate: it is inappropriate to expect a Scout to invest the time detailed planning takes only to face the prospect of rejection.

    Usually comes after 9.0.2.9. Work with the project coach.

Stage 11 of 16

1 step

Stage 12 of 16

1 step

Stage 13 of 16

1 step
  • 9.0.2.8. Complete the project report Document

    In most cases a Scout should fully complete the proposal and the report, and be strongly encouraged to complete the plan. The workbook must not become a basis for rejecting a candidate on technicalities that have nothing to do with the intent of the requirement.

    Usually comes after 9.0.2.4. Carry the project out.

    The workbook is required and it is not a checklist. Where filling in missing information or chasing a signature from somebody unavailable would be a hardship or a poor use of time, and it is clear the project was completed and approved, it is appropriate to accept it. Boards of review should ask whether the project met the requirement, not whether every line was filled in.

Stage 14 of 16

1 step

Stage 15 of 16

1 step
  • 9.0.2.13. Approval withheld: submit anyway May not apply Often forgotten Task

    Where the candidate believes the project as completed meets the intent of requirement 5, it is appropriate to submit the rank application and the workbook without final approval, and if requested the Scout must be granted a board of review. If a unit board may not give a fair hearing, a board under disputed circumstances may be initiated.

    You have not answered "Did the beneficiary and the unit leader approve the finished project?" yet.

    Usually comes after 9.0.2.13. The beneficiary and the unit leader approve the finished project.

    Discuss the risk with the Scout before taking this route, because the board may decide negatively. But the Guide is clear that beneficiaries unfamiliar with the process do sometimes decline over last-minute additions or a change of management, and in those cases it is appropriate to go forward and for the board to understand the requirement was met regardless.

Stage 16 of 16

1 step

This plan is a planning aid: the current Boy Scouts of America publication is always the authority, and the sources used here are listed in full. Each step names its own.